Outline Project Plan
The outline of the Consultation approach adopted is as follows;
October 2016 – September 2017. Consultation Phase 1
October 2016 – March 2017
Prepare presentation media
April 2017 – June 2017
Consultation with public and businesses
– Level 1 questionnaire for residents and business questionnaire
– Workshops (held in May and June 2017)
July/August 2017
Analyse results (Appendices ) and set up Working Groups
September 2017
Present results to Steering Group and sign off
October 2017 – December 2019. Consultation Phase 2
October 2017 to March 2018
Working Groups (covering housing, infrastructure and environment)
Gather evidence from local sources and BDC
Obtain grant money and initiate survey for Character Landscape Assessment (November 2017) (report available from Parish Clerk and as Appendix of NP report )
Obtain grant money to design, publish and distribute level 2 questionnaire
Undertake sustainability appraisal on potential housing development sites (Appendix of NP report)
Identify Vision Statement for NP, objectives, policy options and potential housing sites
April 2018 to September 2018
Design Level 2 questionnaire to identify preferred policy options
Distribute Level 2 Questionnaire to all households in Parish
Collate and analyse questionnaire results
Present results to Steering Group and sign off
October 2018 to December 2018
Undertake ‘Call for Sites’ exercise
January 2019 to June 2019
Collect base line information and complete more detailed sites assessment
More fully develop Green Infrastructure Strategy
July 2019 to December 2019
Audit review of sites assessment work by independent consultants (AECOM)
Housing Needs Assessment study by independent consultants (AECOM)
Urban Design Codes study by independent consultants (AECOM)
Review NP objectives and policies
January 2020 – February 2021. Consultation Phase 3
January 2020 to April 2020
Finalise draft NP report and submit for approval
May 2020 to September 2020
Prepare for ‘Regulation 14’ 6 week statutory consultation
End September 2020 to End October 2020
Undertake 6 week consultation with workshop and events
November 2020 to January 2021
Collate responses and feedback
– Review policies and all documentation
– Finalise NP report and other required documentation
January 2021
Submit statutory documentation to Parish Council
February 2021
Parish Council submit statutory documentation to BDC